王興龍
摘要:
為進一步探索提升裝配式住宅施工速度的方法,推廣裝配式住宅在實際工程項目中的應用,以合肥禹州郎溪上里2#樓施工組織設計為例,對裝配式住宅施工組織設計過程中能夠提升施工進度的具體因素進行分析。分析表明:裝配式結構雖然在施工速度方面具有較強的優勢,但是裝配式結構對施工組織設計具有較高的要求。
關鍵詞:裝配式結構;施工組織設計;進度管理
中圖分類號:TU745.1 文獻標志碼:A
文章編號:2095-5383(2018)02-0040-03
Research on Construction Organization Design
and Progress Management of Prefabricated House
WANG Xinglong
(Department of Architecture and Civil Engineering,Zaozhuang Vocational College of Science&Technology,Tengzhou 277599, China)
Abstract:
In order to further explore the method of improving the construction speed of prefabricated house, and promote the application of prefabricated house in practical engineering projects, the construction design of No. 2 building in LangxiShangli, Hezhou, Hefeiwas taking as an example to analysis the concrete factors that can enhance the construction progress.The results show that although the fabricated structure has a strong advantages in the construction speed, the fabricated structure has higher requirements for construction organization design.
Keywords:
fabricated structure; construction organization design; progress management
近年來,建筑產業化已經成為住宅市場發展的重要趨勢,裝配式結構作為建筑產業化發展的重要基礎也得到進一步拓展。其次,裝配式結構在施工過程當中不僅速度較快,同時也能避免對環境造成較大的污染與破壞,還能有效降低能源消耗[1]。因此,進一步推廣裝配式結構在住宅建筑中的應用具有非常重要的意義。在裝配式住宅施工過程中,施工組織設計是施工的核心,只有做好施工組織設計才能充分發揮裝配式結構在施工效率方面的優勢,并進一步提升生產效率[2]。因此,本文從施工組裝設計的角度對提升裝配式住宅施工進度的重要因素進行分析。
1 工程概況
合肥禹州郎溪上里小區位于安徽省合肥市,其中2#樓為合肥市住宅產業化實驗項目,采用裝配式結構。2#樓總建筑面積為32 123.4 m2,結構形式為預制剪力墻結構,地下一層,地上11層,層高2.9 m,建筑總高度37.23 m。本工程項目設計使用年限為50 y,7度抗震設防,地基設計等級甲級。……