杜平






摘 要:本文以南通市中央創新區醫學綜合體項目為例,重點介紹了BIM+智慧工地技術在實踐項目中的應用,主要包括項目進度管理、項目人員管理、工程質量與安全管理、數字工地建設、BIM建造管理、高支模監測、用電檢測以及環境監測等具體內容。實踐表明,BIM+智慧工地技術的合理應用,強化了工程項目現場管理的科學性與高效性。
關鍵詞:BIM技術;智慧工地;中央創新區;綜合體項目;技術應用
中圖分類號:TU17;TU71 文獻標識碼:A 文章編號:1003-5168(2019)32-0008-03
Application of BIM + Smart Construction Site Technology in the Medical
Complex Project of Nantong Central Innovation District
DU Ping
(Jiangsu Nantong No. 2 Construction Engineering (Group) Co., Ltd.,Qidong Jiangsu 226200)
Abstract: Taking Medical Complex Project as an example, this paper focused on the application of BIM + smart construction site technology in practical projects, mainly including project progress management, project staff management, engineering quality and safety management, digital site construction, BIM construction management, high support mold monitoring, electricity detection, and environmental monitoring. Practice has shown that the reasonable application of BIM + smart construction site technology has strengthened the scientific and efficient management of project site management.
Keywords: BIM technology;smart construction site;central innovation district;complex project;technology application
1 工程概況
南通市中央創新區醫學綜合體(一期)項目由江蘇南通二建集團有限公司承建,建設單位為南通市中央創新區醫學資產管理有限公司,總建筑面積約為64 509.72m2。項目建設期間有效應用了BIM+智慧工地技術,分別對BIM 5D生產應用情況、項目質量應用情況、項目安全應用情況以及項目勞務應用情況等進行了綜合分析。本文主要對BIM+智慧工地技術在南通市中央創新區醫學綜合體(一期)項目中的應用進行具體說明,重點說明項目進度管理、項目人員管理、工程質量與安全管理、數字工地建設、BIM建造管理、高支模監測、用電檢測以及環境監測等具體內容[1]。
2 BIM+智慧工地技術項目應用
2.1 進度管理
項目工程部每周進行任務派發,每條任務具體落實到每個施工員,施工員通過手機端及時反饋任務進度,平臺形成統一數據,分析完成情況和延期情況等,生產經理根據數據分析進行調整優化,導入總計劃,生成關鍵節點[2]。BIM+智慧工地技術的應用對項目進度控制具有顯著效果,從上至下智能化地下發任務命令,通過信息系統進行項目進度的實時控制,項目實施進度管理系統模塊如圖1所示。……