摘 要:本文介紹了一套實用性很強的圖紙設計進度管理系統。為了滿足當前建筑設計公司體制的需要,通過系統軟件平臺實現對圖紙設計進度的監督和管理,利用里程碑的進度管理思想縮短工期。該系統解決了圖紙設計中各專業設計人員的自定義工程進度、不同專業之間的協同配合的問題;提供實時的進度報告和進度監測,保證數據資料分析和調整措施的科學性和及時性。系統具有層次清晰的項目分類和任務列表,明確任務負責人,時間截止點;可以使使用者告別繁瑣費時的會議,實現進度跟蹤,績效評估,從而提高執行力。
關鍵詞:進度管理;里程碑模式;平行設計
中圖分類號: TP311 文獻標識碼:A 文章編號:2096-4706(2018)11-0063-04
Design of Progress Management System for Architectural Drawings Based on
Milestone Mode
YUAN Bo,DAN Shouyang
(School of Electronics and Information Engineering,Jinggangshan University,Ji’an 343009,China)
Abstract:This paper introduces a set of practical drawing design progress management system. Through the system software platform to realize the supervision and management of the drawing design progress. It can not only meet the requirements of the current system,but also shorten the construction period by using the idea of schedule management of the fast path method. The software system mainly solves the problems of customized progress and collaborative work among different design specialties,including a sound progress reporting system and progress monitoring system to ensure the scientific and accurate data analysis and adjustment measures. The system has a clear hierarchy of project classification and sub-parent task list,clear task owners,deadlines;users can bid farewell to frequent and inefficient meetings;achieve data tracking,control progress and results,improve execution.
Keywords:progress management;milestone mode;parallel design
0 引 言
隨著建筑行業步入成熟發展期,進度控制也引起了越來越多的企業管理者和項目經理的重視,有效的管理成為建筑企業發展關注的新方向,項目進度管理是新的競爭點,企業競爭力是強是弱,與施工項目進度管理的優劣有著密切的聯系。但是在實際施工過程中,受到政策、市場、自然環境的影響,工程的實際進度與計劃經常不一致,工程項目的實際進度不斷產生著各種情況的變化。在這種情況下,項目負責人就必須做出科學、及時的修改,不然就會影響工程項目的總進度,進而影響投資成本和收益。因此要想工程項目能夠如期順利地實現預定目標,就必須對施工項目進度進行及時、有效的管控。項目進展的……