摘" 要:為科學制定土方調配方案,降低工程成本和造價,首先通過方格網法計算土方工程量,然后運用運籌學中的運輸問題建立模型,再運用表上作業法進行土方調配方案的優化,從而明確挖方與填方區的土方調配方向和數量,最終達到滿足設計標高的同時成本最低。最后在充分考慮調配方案目標的基礎上,提出相應的目標規劃模型。
關鍵詞:方格網法;運輸問題模型;表上作業法;土方調運;目標規劃
中圖分類號:TU751" " " 文獻標志碼:A" " " " " 文章編號:2095-2945(2024)33-0136-05
Abstract: In order to scientifically formulate an earthwork allocation plan and reduce project costs and costs, first calculate the earthwork volume through the grid method, then use the transportation problems in operations research to establish a model, and then use the table operation method to optimize the earthwork allocation plan, thereby clarifying the direction and quantity of earthwork allocation in the excavation and fill areas, and ultimately achieve the lowest cost while meeting the design elevation. Finally, based on fully considering the goals of the deployment plan, a corresponding goal planning model is proposed.
Keywords: grid method; transportation problem model; table operation method; earthworks allocation; goal planning
施工場地平整是指將天然地面改造成工程上所要求的設計平面,由于場地平整時全場地兼有挖和填,而挖和填的體形常常不規則,所以在場地平整前首先要對場地內的土方量進行計算。目前常用的計算方法有斷面法、方格網法、DTM法和等高線法[1]。袁偉等[2]通過計算得出,方格網法計算的成果與DTM法計算的成果基本一致,其相對誤差均在3%以內,說明2種方法計算的成果均可靠。故本文首先采用方格網法分塊計算土方體積,然后運用運籌學中的運輸問題模型解決土方調運的問題。在大型土方工程施工時,為了達到降低成本節約工期的目的,常常需要運用這樣一些方法來制定可行的土方調運方案,以指導施工[3]。而在實際生產現場,許多施工人員僅憑自己積累的常識和經驗粗略確定一個土方調配方案,這樣不合理的土方調配方案容易造成土方的重復挖填和大量的土方運輸,勢必造成工程成本的提高。……