劉須朋



摘 要:本文通過對泗陽二站機組大修過程中,電機定子與水泵軸窩同心度調整合格后,電機定子需吊出,裝入水泵大軸,電機定子二次吊入,采用雙孔一面定位的技術方法,保證機組的同心度位置不變,順利解決機組大修中的技術問題,保證了機組的大修質量,為同類型機組大修時,提供參考借鑒。
關鍵詞: 機組大修; 同心度; 雙孔一面定位
Abstract: This article is to introduce these aspects, during the process of unit overhaul of Siyang Second Pumping Station, after adjusting stator and the concentricity of pump shaft, stator should be lifted out, and then placing pump shaft, and lifting out stator again. This adopts the technical approach of side positioning holes to ensure the invariability of units location of concentricity, and to solve the technical question during the process of unit overhaul smoothly. At the same time, it could ensure the quality of unit overhaul, For same type unit overhaul when,Provide reference learn.
Key words: Unit overhaul; Concentricity; Side positioning holes
1.引 言
泗陽第二抽水站(下稱泗陽二站)位于江蘇省泗陽縣城東郊,是江蘇省江水北調第四梯級站,淮水北調第一梯級站,其主要作用是抽引由二河閘下泄的淮水或淮陰站轉送的江水北送,滿足泗陽閘上游地區的用水需求。
該站建成于1996年,工程總投資6300萬元。總裝機容量5600KW,設計流量為66m3/s。裝設2.8ZLQ-7.0液壓全調節軸流泵2臺,單機流量33 m3/s,配套TDL325/56-40立式同步電機,電機與水泵采用剛性聯軸器直聯方式。泵站采用堤身式結構,肘形進水流道,虹吸式出水流道,真空破壞閥斷流。
2.泗陽二站機組情況及大修的工藝特點
泗陽二站機組由于設計、制造問題,水泵大軸下法蘭直徑比電機下油缸內孔直徑大5mm,水泵大軸不能通過電機下油缸內孔吊出,電機定子下機架聯接為一體,如圖1,電機定子通過下機架的4條支腿,每個支腿底鋼板(40cm×60cm×4.5cm)與混凝土基礎梁鋼板(60cm×60cm×4.5cm)由兩顆M48螺絲緊固聯接,地腳螺絲孔比M48地腳螺絲外徑大2mm。
因此,泗陽二站的機組大修就不能采用常規的機組大修工藝,在機組大修時,必須把同步電機全部拆除,才能把水泵軸吊出,便于零部件檢修;……